Deadline extended for Administration Centre project
Published: October 02, 2013
During his inspection visit to the construction site of the new Da Nang Administration Centre on Tuesday, the municipal People’s Committee Chairman, Mr Van Huu Chien, agreed to extend the deadline for fully completing the project to 30 November.
All construction units pledged to complete the whole project by 30 November 2013 |
The city’s Management Board for Construction Projects said that 100% of the main construction work has already been completed. However, the installation work is 30 days behind schedule, and the installation of the outer glass and aluminum frames on the 33rd storey is 60 days behind schedule. The main reasons given are the delays in site clearance work, and in importing materials and equipment from foreign manufacturers.
.