Cam Le Industrial Cluster project expected to come on stream soon

By DA NANG Today / DA NANG Today
June 03, 2021, 11:35 [GMT+7]

More than 90% of the workload on the first stage of the Cam Le Industrial Cluster project in Hoa Tho Tay Ward, Cam Le District, Da Nang, has been completed, said the municipal government. 

The first stage of the project, whose construction started in June 2019, features major work items such as leveling, traffic, drainage, water and electricity supply, and landscaping and wastewater treatment systems worth more than VND 58 billion in total.

Meanwhile, work started on the second stage of the project in March at a cost of more than VND53 billion, and 10 - 15% of the workload has reached completion.

Covering a total area of 29 ha, the Cam Le Industrial Cluster project is being carried out in the 2018 - 2022 period with a total cost of VND 250 billion funded by the municipal budget.

The Cam Le District People's Committee is the developer of the project 

Reporting by NAM PHUONG – Translating by A.T

.
.
.
.