Damaged Tuy Loan intersection with Da Nang - Quang Ngai Expressway about to be repaired for traffic safety

By DA NANG Today / DA NANG Today
June 19, 2022, 18:51 [GMT+7]

After many years of delay, the Tuy Loan intersection, located on National Highway 14B in Hoa Vang District, at the beginning of the nearly 140km Da Nang - Quang Ngai Expressway, is about to be repaired for the sake of traffic safety.

Defects are seen at the Tuy Loan Intersection that is located at the beginning of the Da Nang - Quang Ngai Expressway. (Photo taken in May 2022). Photo: THANH LAN
Defects are seen at the Tuy Loan Intersection that is located at the beginning of the Da Nang - Quang Ngai Expressway. (Photo taken in May 2022). Photo: THANH LAN

The Viet Nam Expressway Corporation (VEC), the developer of the Da Nang - Quang Ngai Expressway has just approved the results of selection of a contractor to repair the Tuy Loan intersection which has been heavily damaged for many years and became an accident-prone hotspot.

The joint name between Luc Viet Construction JSC and My Toan Construction Investment JSC.  The bidding package is estimated at more than 4 billion VND and the implementation time is 60 days.

It is known that the winning bid price is more than VND 3.9 billion and the warranty period for the project is 12 months since the work passed a mandatory technical acceptance testing.

During the warranty period, if damage occurs to construction items, the contractor needs to fix it within 24 hours from the time of receiving the investor's notice.

Reporting by THANH LAN – Translating by A.THU

.
.
.
.