Da Nang targets to complete site clearance for 100 projects in 2023
After Tet, the Da Nang government has issued a site clearance and compensation plan for 202 projects in the city. Currently, relevant units and localities are urgently making every effort to complete the site clearance and compensation work for 100 projects in 2023 with 10,008 related dossiers.
Starting from February 1 (the 11th day of the first lunar month), the Basic Construction Management Board of Hai Chau District dismantles a number of houses and works surrounding the Chi Lang Stadium that had been handed over by the owners to the Management Board. |
Drastic solutions after Tet
On February 1 (the 11th day of the first lunar month), the Basic Construction Management Board of Hai Chau District dismantled a number of houses and works surrounding the Chi Lang Stadium that had been handed over by the owners to the Management Board.
Before Tet, following the direction from the Chairman of the Hai Chau District People's Committee, the Management Board installed aesthetic steel fences combined with panels with pictures of the district, and planted some types of trees along the fence, creating an airy and beautiful landscape along Le Duan and Ngo Gia Tu streets.
Head of the Hai Chau District’s Basic Construction Management Board Dang Van Hieu said, currently, 89 out of the 100 households and shops around the Chi Lang Stadium have handed over the premises.
Due to rainy weather and a number of objective reasons before Tet, the demolition work has yet to be completed. Therefore, from early February, the district authorities started the work, he informed.
According to the district authorities, 9 households with residential land records and 2 organisations under the project of a high-rise commercial and service complex at the Chi Lang Stadium have not yet handed over the premises.
The district will focus on encouraging 9 households and 2 organisations to hand over the premises in the first quarter and in the second quarter of this year respectively.
Aside from the abovementioned project, the Hai Chau District People's Committee strives to complete site clearance for 3 other projects in 2023 with 9 compensation and site clearance dossiers.
Also on February 1, Vice Chairman of the Son Tra District People's Committee Huynh Van Hung checked the actual clearance for the Vo Duy Ninh Street Renovation and Upgrade Project in Tho Quang Ward.
Within the scope of the project, 58 residential houses and land lots, 6 agricultural land lots, 2 other land lots in need of compensation and clearance and 5 graves have not been relocated yet.
The district authorities are making every effort to solve problems and pay compensation to ensure that 15 premise handover agreements will be signed in the first quarter of this year and 20 others in the second quarter.
"The district strives to complete the site clearance of the Vo Duy Ninh Street Renovation and Upgrade Project in 2023" Mr. Hung noted.
In 2023, Son Tra District plans to carry out site clearance work for 28 projects including 1,449 house, land and construction site clearance documents and 1,580 graves that need to be relocated. The total cost of compensation and site clearance work is expected to be VND105 billion according to the plan. In which, there will be 11 projects that are required to get site clearance work done in 2023.
Following the direction from Chairman of the municipal People's Committee Le Trung Chinh at the meeting with leaders of Cam Le District on January 11, 2023 to discuss the construction of the Cam Le Industrial Cluster before June 2023, the district is urgently solving problems and mobilising one household left to hand over the premise to construction units.
The important project is expected to create a growth engine for the whole city, Chairman Chinh emphasised.
Focus on site clearance for key and motivational projects
In 2023, Hoa Vang District plans to deploy 46 projects with 7,798 compensation dossiers for clearing houses, land and construction works and 1,877 graves.
In which, 20 projects with 3,926 compensation dossiers for clearing houses, land and works and 1,872 graves will have site clearance work done in the year. The site clearance for the remainder will be completed in 2024.
In order to achieve its target, the district is paying special attention to completing the site clearance work for key and motivational projects. These projects include the DT.601 road and National Highway 14B upgrade and extension, Western Ring Road, Hoa Nhon Industrial Cluster, Hoa Phuoc Wholesale Market, and Hoa Lien - Tuy Loan expressway as part of the North-South expressway east of Da Nang.
At present, Lien Chieu District is trying to solve problems and complete the site clearance for the remaining 4 cases affected by the Nam O eco-tourism area, drainage canal and isolated green line of Hoa Khanh Industrial Park, and Area No. 1 - Northwest New Urban Center projects in the first quarter of this year. Also, heed will be on completing site clearance for the remaining 28 cases affected by the Lien Chieu Wastewater Treatment Station, Hoa Hiep 3 Resettlement Area in phase 2, and the extended Hoa Hiep Resettlement Area projects no later than April 30, 2023.
In addition, the district strives to complete site clearance for 20 projects in 2023 with 1,939 compensation records for clearing houses, land, works and 821 graves, especially such key and dynamic projects as a section of North-West Axis Route 1 from Ho Tung Mau to National Highway 1A, the Lang Van tourist complex and Lien Chieu Seaport.
In the coming year, the district is scheduled to carry out site clearance for 14 projects with 2,157 clearance dossiers of houses, land and works and 2,819 graves.
It is known that in 2023, the whole city will carry out site clearance work for 202 projects with 18,393 compensation dossiers for house, land and works. Of which, the site clearance of 100 projects with 10,0008 compensation and clearance documents is slated to be completed in 2023, whilst that of the remaining 102 projects will be completed in 2024.
Reporting by HOANG HIEP - Translating by M.DUNG