Da Nang speeds up progress of industrial parks, clusters

By DA NANG Today / DA NANG Today
September 21, 2022, 15:15 [GMT+7]

For the time being, in addition to the Cam Le industrial cluster (IC) on which infrastructure construction is scheduled to reach completion in October, functional sectors Da Nang-wide are rushing to spur up promote investment in the construction of many new industrial parks (IPs) and ICs.

The infrastructure construction in the Cam Le IC is expected to be basically completed in October. Construction units are observed completing many work items at the Cam Le IC Photo: KHANH HOA.
The infrastructure construction in the Cam Le IC is expected to be basically completed in October. Construction units are observed completing many work items at the Cam Le IC Photo: KHANH HOA.

Speed up infrastructure construction, call for investors

Given the drastic direction of the Da Nang authorities, many ICs are gradually taking the shape after a long time of construction. Till data, the site clearance work has been completed at the Cam Le IC project in the namesake district has basically completed whilst 95% of the workload of Phase 1 bidding package and 65% of Phase 2’s has been completed with a total of 8 main items.

As reported by Mr. Le Trung Duong, Head of Cam Le District Management Board of Construction Investment Projects, the infrastructure construction is expected to be basically completed  in October and this will be followed by an acceptance test to pave the way for putting the project into operation.

In Hoa Vang District, many IPs and ICs have been planned, in which, the industrial park project to the support park in service for the Da Nang Hi-tech Park, Hoa Nhon IC and the Hoa Son split stone village.

Mr. Ngo Ngoc Truc, Deputy Head of Hoa Vang District Economic and Infrastructure Department, said that the district is coordinating with other competent agencies to carry out bidding procedures, call for investment into the24.7 ha Hoa Nhon IC.

The municipal Department of Industry and Trade has asked for approval fom the municpal People's Committee for a set of criteria for selecting technical infrastructure investors in the Hoa Nhon IC for attracting investment.

As revealed by the Authority of the Da Nang Hi-Tech Park and Industrial Zones (DHPIZA), currently, functional agencies are accelerating the completion of investor selection for infrastructure investment projects in Phase 2 of the Hoa Cam IP, the Hoa Ninh and Hoa Nhon IPs.

As for the Hoa Ninh IP, the procedures for converting forest land use purpose is expected to be competed in September 2022. By the fourth quarter of 2022, investors will be selected for infrastructure  investment and construction if the Prime Minister approves the investment policy in this quarter.

Meanwhile, following approval by the municipal People's Committee on a total investment of VND 2,200 billion poured into Phase 2 of the Hoa Cam IP, the Da Nang Department of Planning and Investment is appraising the preliminary requirements for the investor's capacity and experience eligible for infrastructure investment in this IP.

Many industrial zones and clusters are carrying out procedures and documents for site clearance. The Hoa Nhon IC in Hoa Vang District is facing problems in site clearance. Photo: KHANH HOA
Many industrial parks and clusters are carrying out procedures and documents for site clearance. The Hoa Nhon IC in Hoa Vang District is facing problems in site clearance. Photo: KHANH HOA

A push to complete procedures for development of IPs, ICs

Regarding the specific progress of the remaining projects of IPs and ICs, Mr. Pham Truong Son, Head of the DHPIZA, the planning area of the Hoa Nhon IP has been downwardly adjusted to 237ha from 360.1ha as previously planned.

After having the adjusted planning, it will advise the City People's Committee to submit to the Prime Minister for approval the investment policy, organize the selection of investors. Also on the basis of the proposal of the Management Board, the City People's Committee assigned the Department of Planning and Investment to assume the prime responsibility for handling issues related to the legal basis for putting into operation and the mode of operation of the Industrial Park in support of the Da Nang Hi-tech Park.

As for the expansion of the Da Nang Hi-Tech Park, following appraisal of the project budget estimates by the municipal Department of Finance, the DHPIZA has submitted a report to the municipal People's Committee for approval on the outline and cost estimate for project formulation.

In particular, DHPIZA has already proposed the municipal People's Committee to halt the relocation of the Da Nang Industrial Park (IP), also known as the An Don IP based in Son Tra District and make payment to consulting units according to the performed work volume.

In 2017, the Vietnamese Prime Minister has given the go-ahead to the conversion of current industrial land at the Da Nang IP into urban land. However, according to the provisions of the national laws on Planning and Construction, the planning for Da Nang IP should be consistent with the Da Nang Master Plan for the city’s major developements by 2030, with a vision towards 2045 approved by the Prime Minister.

In addition, in the process of making detailed planning, technical infrastructure planning must also be made. Currently, the entire technical infrastructure system, including transportation, electricity and water supply, wastewater treatment in the Da Nang IP is the property under the management of Massda Land Co., Ltd. - the investor of the Da Nang IP. Therefore, the planning of technical infrastructure to match the new plan may take a long time to implement.

Reporting by KHANH HOA – Translating by A.THU

.
.
.
.