The Da Nang Water Supply JSC has invited bids for the bidding package ‘Construction, supply and installation of clean water tank technology and sludge treatment system’ as part of a project on increasing the capacity of Hoa Trung Lake Water Plant from 10,000m3/day and night to 20,000m3/day and night.

Accordingly, the bidding package is priced at more than VND 8 billion, which is widely auctioned online. The implementation duration of the contract will last 120 days.

Work started on the VND80 billion Hoa Trung Lake Water Supply Plant with a capacity of 10,000m3/day and night, located in the Da Nang Hi-Tech Park, Hoa Lien Commune, Hoa Vang District, in mid-2018, and the construction work was completed in July 2019. The 2nd stage of Hoa Trung Lake Water Plant is under construction at a total cost of about VND15 billion.