The traffic route connecting DT601 Road and Loc My Village in Hoa Bac Commune, Hoa Vang District, Da Nang is expected to open to traffic on August 28, 2024. Once operational, it will significantly contribute to completing the traffic network according to the plan, and boosting the local socio-economic development.
|
The traffic route project connecting DT601 road and Loc My village is a level 3 project with a total investment of more than VND93 billion. Work started on the project in December 2022 and is expected to open to traffic on August 28, 2024 to marke the National Day (September 2). |
|
The project is invested by the People's Committee of Da Nang, and is managed by the Da Nang Management Board of Traffic Construction Investment Projects. The DACINCO Construction Investment Company Limited and the 510 Construction JSC are the main contractors. |
|
The main items of the project include the main approach road, a connecting road, a bridge over Cu De River and a bridge over Bau Bang Stream, creating 3 spacious traffic branches in Hoa Bac Commune. |
|
The main approach road is 872.17m long. Its starting point connects with DT601 road at Km13+250, whilst its ending point connects with Bac Thuy Tu - Pho Nam route at Km14+950. |
|
The main approach road is 7m wide with each side's sidewalk of being 1m wide. It has A1 high-class road surface structure. |
|
Meanwhile, the approach road connecting to Loc My Village is 299.38m long, with starting point at the intersection of the Loc My Village, and ending point at the main approach branch at Km0+685. The road surface is 5.5m wide, and each side's sidewalk is 1m wide. The structure of the road surface is high-class A1. |
|
The Cu De Bridge crossing the namesake river (Km0+499.65) has a total length of 118.30m. |
|
The Cu De Bridge is designed with a 7.5m wide roadway and a 1.5m wide pedestrian lane on each side. |
|
The Bau Bang Bridge over the namesake Stream (Km0+811.57) is adjacent to the intersection at the end of the route. It has a prestressed reinforced concrete beam span with the length of 38.3m. |
|
The Bau Bang Bridge has a 7.5m wide roadway and a 1.5m wide pedestrian lane on each side. |
|
Technical infrastructure systems including traffic signs, road markings, negative slopes, and lighting on the route have been ready for opening to traffic. |
|
After being open to traffic, the traffic route connecting DT601 road and Loc My Village will complete the traffic network according to the planning, and create an additional connection route between Bac Thuy Tu - Pho Nam road and DT601 road in Hoa Bac Commune, thereby connecting Nam My Village and Loc My Village. |
|
This route will contribute to reducing traffic overload on Truong Dinh Bridge (Hoa Lien Commune), and Pho Nam Bridge (Hoa Bac Commune), solving traffic congestion in rescue work, and shortening the distance to the centre of Hoa Bac Commune. |
Reporting by XUAN SON - Translating by M.DUNG, P.TRA
.